Your Trusted Partner for a Bathroom Remodel in Williamsburg
As the leading home improvement contractor in Williamsburg, VA we have done tons of bathroom remodels every year. Every project is different, but our goal is to be as transparent and honest with you as possible. Every time we start a conversation about bathroom remodeling one of the first questions, we get asked how long will it take. The short answer as always is depends. We broke the project into three sizes with three different timelines. With all the variables in remodeling this timeline is based on averages and experience.Â
Powder Room:
Timeline: 1-2 Weeks
Scope of Work: New flooring, vanity, faucet, toilet, electrical and painting
Guest Bathroom: 8ft x 5ft appx
Timeline: 2-4 Weeks
Scope of Work: New tub/shower surround, plumbing, electrical, flooring, vanity, toilet, drywall and painting
Primary Bathroom Remodel: 10ft x 10ft or larger
Timeline: 4-8 Weeks
Scope of Work: New tub, new shower, flooring, double vanity, toilet, drywall, misc trim, more plumbing, more electrical and painting.
If you have any questions about bathroom remodel timing or pricing, please give us a call and we can guide you through the remodel process.